91原创

Skip to content

Fifth Trans Mountain pipeline-related sinkhole since April concerns 91原创 farmer

He estimates the latest sinkhole was up to 30 feet deep

The fifth sinkhole to appear on or near 91原创 Township Councillor Rob Rindt鈥檚 property has him worried about the safety of his family and staff.

The sinkhole appeared Saturday, June 10 near the site where contractors for Trans Mountain are drilling underground as part of the extension of the oil pipeline that runs from Alberta to a refinery in Burnaby.

鈥淚t just seems to be getting deeper, and the whole road is sinking into the ground,鈥 said Rindt, who owns a turf farm on several properties on either side of 240th Street, as well as the Roots and Wings Distillery.

The first four sinkholes appeared on his property or nearby in April and May, and damaged 240th Street to such an extent that traffic had to be restricted to one lane on 240th Street between 80th Avenue and 72nd Avenue for several days in May while repairs were made.

The new sinkhole is on the edge of Rindt鈥 s property near the road, and he estimates it was up to 30 feet deep. Several truckloads of gravel have been dumped into it, but Rindt believes it鈥檚 still sinking somewhat.

鈥淭hey brought another load [of gravel] yesterday,鈥 Rindt said Thursday, June 15.

He said he was planning to talk to his lawyer about the situation.

鈥淢y main concern at this location is, what鈥檚 going to happen in the future, and are they going to fix it up properly?鈥 Rindt said.

His staff work in the fields there, and his children play on that land, Rindt said. He鈥檚 concerned about future sinkholes creating a hazard for them.

READ ALSO: VIDEO: Trans Mountain confirms sinkholes on 91原创 pipeline project site

The pipeline stretches across the fields of Rindt鈥檚 turf farm, and also affects a potato field that serves the distillery.

Rindt also owns some farmland in Abbotsford, which was also cut through by the pipeline.

The 91原创 Advance Times asked Trans Mountain鈥檚 media relations portal a number of questions about the causes and number of sinkholes. Trans Mountain provided a statement.

鈥淎s is the case with the trenchless crossing under 240th Street in 91原创, we do encounter challenging ground conditions that occasionally result in the formation of sink holes, which is not unexpected,鈥 the statement said. 鈥淲ork sites are continuously monitored and should a sink hole occur it is immediately stabilized. Once construction is completed the sink hole is permanently repaired.鈥

The site where the sinkholes have formed is where the company has started to drill underground to lay pipeline, rather than the usual method of digging a trench and installing the pipe directly. The 鈥渢renchless鈥 method is used to get past waterways, environmentally sensitive locations, highways, and railways.

Doug Hawley, the general manager of the Redwoods Golf Course in Walnut Grove, said that there were a couple of small sinkholes created there were the Trans Mountain pipeline used drilling to get under some major trees without removing them.

鈥淚t鈥檚 not as good as it sounds,鈥 he said of the trenchless method. Fortunately, he said the golf course鈥檚 sinkholes were filled in and are not in areas of play.

The pipeline was originally being constructed by Kinder Morgan, which wanted to add capacity to an existing pipeline that was built in the 1950s to connect oil producing regions of northern Alberta with the coast.

The new, additional pipeline will almost triple the capacity of the original line. However, because there had been a significant amount of development in the Lower Mainland since the first line was built, the new line doesn鈥檛 always follow the same route.

The pipeline was taken over by the federal government in 2018, purchased from Kinder Morgan for $4.5 billion.

The cost of the project was originally estimated at $12.6 billion. That was increased to $21.4 billion in 2022, and this March, the price tag ballooned again to an estimated $30.9 billion.

Meanwhile, the project has already missed its expected completion date of 2022, and is now projected to be up and running in early 2024. That delay has impacted the landowners whose properties are on the pipeline routes.

In 91原创, for example, the Redwoods Golf Course is closed a year longer than planned, although Hawley said it is now looking like things are on schedule and the course will open for late spring next year.

READ ALSO: Trans Mountain pipeline construction costs balloon again, this time to $30.9B

READ ALSO: 91原创鈥檚 Redwoods to stay closed to golfers until 2024


Have a story tip? Email: matthew.claxton@langleyadvancetimes.com
Like us on and follow us on .


Matthew Claxton

About the Author: Matthew Claxton

Raised in 91原创, as a journalist today I focus on local politics, crime and homelessness.
Read more



(or

91原创

) document.head.appendChild(flippScript); window.flippxp = window.flippxp || {run: []}; window.flippxp.run.push(function() { window.flippxp.registerSlot("#flipp-ux-slot-ssdaw212", "Black Press Media Standard", 1281409, [312035]); }); }