Construction means traffic slowdown on rural 91Ô­´´ roads

216th, 40th Avenue to be impacted this month
web1_flagger-2653402_1920
Traffic will be delayed on some 91Ô­´´ Township roads over the next few weeks for construction. (Image from Pixabay)

Repaving and utilities work will impact some rural roads in 91Ô­´´ south and east of Murrayville this month.

Paving was scheduled to take place on 216th Street, from 40th to 44th Avenue, weekdays between Oct. 16 to 27, according to a Township of 91Ô­´´ announcement.

The roadwork, which was weather-dependent, was to run from 7 a.m. to 7 p.m. each day, with single-lane alternating traffic, controlled by flaggers. The Township warned that delays were possible.

Not far away, utilities work was set to take place on 40th Avenue between 232nd and 240th Streets from Oct. 23 to 27.

There was expected to be single-lane alternating traffic at that site as well, with work running from 7 a.m. to 5 p.m. each day.

Weather issues could delay or extend work at either site.

For more information and updates, residents were advised to visit .

READ ALSO: Section of 208th Street partially closed until March, Township says